| Priority | Definition | Planning Window | Execution Window | |----------|------------|----------------|------------------| | P0 (Emergency) | Imminent HSE or major production loss | 0 hr | Immediate | | P1 (Urgent) | Significant degradation | 4-8 hrs | 24 hrs | | P2 (Planned) | Routine corrective/preventive | 2 weeks | 4 weeks | | P3 (Deferrable) | Minor improvement / low risk | Next shutdown | Next opportunity |
- Maintenance Planner / Scheduler - Operations Authority - Maintenance Supervisor - Contractor / Vendor - CMMS Data Steward work management system -wms- adnoc pdf
- Technical report & as-maintained data - Feedback loop into maintenance strategy - KPIs data capture (Schedule compliance, backlog) | Priority | Definition | Planning Window |
The ADNOC Work Management System (WMS) provides a standardized framework for the safe, efficient, and reliable execution of all maintenance and operational work across ADNOC Group’s assets. It integrates with the ADNOC Operational Excellence (OE) System and enforces rigorous Permit to Work (PTW) protocols to ensure zero harm, maximum asset integrity, and optimized lifecycle cost. Introduction
5.1 Common PTW workflow (Issuing Authority, Performing Authority) 5.2 Simultaneous Operations (SIMOPS) Management 5.3 Gas test and safety requirements
- A – Typical Work Order Coding Structure (ADNOC) - B – Priority Matrix (Safety, Production impact) - C – Job Safety Analysis (JSA) Template - D – Abbreviations and Definitions Sample Content (Page 1 – Executive Summary Style) 1. Introduction